PUBLIC LAW 96-000—MMMM. DD, 1980

PUBLIC LAW 96-540—DEC. 17, 1980

94 STAT. 3201

unless a period of 30 calendar days (not including any day in which either House of Congress is not in session because of adjournment of more than 3 calendar days to a day certain) has passed after receipt by the appropriate committees of Congress of notice from the Secretary of Energy (hereinafter in this title referred to as the "Secretary") containing a full and complete statement of the action proposed to be taken and the facts and circumstances relied upon in support of such proposed action, or unless each such committee before the expiration of such period has transmitted to the Secretary written notice to the effect that such committee has no objection to the proposed action. (b) In no event may the total amount of funds obligated pursuant to this Act exceed the total amount authorized to be appropriated by this Act. LIMITS ON GENERAL PLANT PROJECTS

SEC. 202. (a) The Secretary may carry out any construction project under the general plant projects provisions authorized by this Act if the total estimated cost of the construction project does not exceed $1,000,000. Qy) If at any time during the construction of any general plant Report to project authorized by this Act, the estimated cost of the project is confmlttees^ revised due to unforeseen cost variations and the revised cost of the project exceeds $1,000,000, the Secretary shall immediately furnish a complete report to the appropriate committees of Congress explaining the reasons for the cost variation. (c) In no event may the total amount of funds obligated to carry out all general plant projects authorized by this Act exceed the total amount authorized to be appropriated for such projects by this Act. LIMITS ON CONSTRUCTION PROJECTS

SEC. 203. (a) Whenever the current estimated cost of a construction project which is authorized by section 102 of this Act, or which is in support of national security programs of the Department of Energy and was authorized by any previous Act, exceeds by more than 25 percent the higher of (1) the amount authorized for the project, or (2) the amount of the total estimated cost for the project as shown in the most recent budget justification data submitted to Congress, the project may not be started or additional obligations incurred in connection with the project above the total estimated cost, as the case may be, unless a period of 30 calendar days (not including any day in which either House of Congress is not in session because of adjournment of more than 3 days to a day certain) has passed after receipt by the appropriate committees of Congress of written notice from the Secretary containing a full and complete statement of the action proposed to be taken and the facts and circumstances relied upon in support of the action, or unless each committee before the expiration of such period has notified the Secretary it has no objection to the proposed action. (b) Subsection (a) shall not apply to any construction project which has a current estimated cost of less than $5,000,000. F U N D TRANSFER AUTHORITY

SEC. 204. To the extent specified in appropriation Acts, funds appropriated pursuant to this Act may be transferred to other agencies of the Government for the performance of the work for which the funds were appropriated, and funds so transferred may be