Beginning of Construction for Sections 45 and 48; Extension of Continuity Safe Harbor to Address Delays Related to COVID-19 and Clarification of the Continuity Requirement


Notice 2021-41

SECTION 1. PURPOSE

This notice clarifies and modifies the prior Internal Revenue Service (IRS) notices[1] addressing the beginning of construction requirement for both the production tax credit for qualified facilities under § 45 of the Internal Revenue Code (Code) and the investment tax credit for energy property under § 48 of the Code. In response to the Coronavirus Disease 2019 (COVID-19) pandemic, this notice provides that the safe harbor originally provided in section 3.02 of Notice 2013-60 and in section 6.05 of Notice 2018-59 and extended in prior IRS notices (Continuity Safe Harbor) is further extended for property the construction of which began in 2016 through 2020. This notice also provides a clarification of the methods that taxpayers may use to satisfy the Continuity Requirement (as provided in prior IRS notices and defined in section 2 of this notice) to satisfy the beginning of construction requirements under §§ 45 and 48.

SECTION 2. BACKGROUND

Section 38 of the Code allows certain business credits. Among the credits allowed by § 38 are the renewable electricity production tax credit under § 45 and the


  1. Notice 2013-29, 2013-20 I.R.B. 1085; Notice 2013-60, 2013-44 I.R.B. 431; Notice 2014-46, 2014-36 I.R.B. 520; Notice 2015-25, 2015-13 I.R.B. 814; Notice 2016-31, 2016-23 I.R.B. 1025; Notice 2017-04, 2017-4 I.R.B. 541; Notice 2018-59, 2018-28 I.R.B. 196; Notice 2019-43, 2019-31 I.R.B. 487; Notice 202041, 2020-25 I.R.B. 954; and Notice 2021-5, 2021-3 I.R.B. 479 (collectively, the prior IRS notices).