1010
43 USC 504 and note.
42 USC* iVss^1855g.
PUBLIC LAW 89-689-OCT. 15, 1966
[80 STAT.
for construction work by force account: Provided, That this paragraph shall not apply to work performed under the Rehabilitation and Betterment Act of 1949 (63 Stat. 724). Any appropriations made heretofore or hereafter to the Bureau of Reclamation which are expended in connection with national disaster relief under Public Law 81-875 as administered by the Office of Emergency Planning shall be reimbursed in full by that Office to the account for which the funds were originally appropriated. BONNEVILLE POWER ADMINISTRATION CONSTRUCTION
For construction and acquisition of transmission lines, substations, and appurtenant facilities, as authorized by law, and purchase of three aircraft, of which two shall be for replacement only, $109,000,000, to remain available until expended: Provided, That the Bonneville Power Administration shall not supply power directly, or indirectly through any preference customer, to any phosphorous electric furnace plant in southern Idaho, Utah, or Wyoming. OPERATION
AND
MAINTENANCE
For necessary expenses of operation and maintenance of the Bonneville transmission system and of marketing electric power and energy, $17,010,000. ADMINISTRATIVE
PROVISIONS
Appropriations of the Bonneville Power Administration shall be available to carry out all the duties imposed upon the Administrator pursuant to law. Appropriations made herein to the Bonneville Power Administration shall be available in one fund, except that the appropriation herein made for operation and maintenance shall be available only for the service of the current fiscal year. Other than as may be necessary to meet local emergencies, not to exceed 12 per centum of the appropriation for construction herein made for the Bonneville Power Administration shall be available for construction work by force account or on a hired-labor basis. SOUTHEASTERN POWER ADMINISTRATION OPERATION AND MAINTENANCE
58 Stat. 890.
For necessary expenses transmission facilities and pursuant to the provisions 1944 (16 U.S.C. 825s), as including purchase of one only, $1,000,000.
of operation and maintenance of power of marketing electric power and energy of section 5 of the Flood Control Act of applied to the southeastern power area, passenger motor vehicle for replacement
SOUTHWESTERN POWER ADMINISTRATION CONSTRUCTION
For construction and acquisition of transmission lines, substations, and appurtenant facilities, and for administrative expenses connected therewith, in carrying out the provisions of section 5 of the Flood Control Act of 1944 (16 U.S.C. 825s), as applied to the southwestern power area, $3,950,000, to remain available until expended.
�